We have used the server configurator (SC from now on) to install 2 sites to our test environment on the same 'single server' jboss server.
From what I can tell there is no indication of what sites are installed from SC.
I also see no way to give a different website URL like we could in the past, SC forces you to use the db name as the website url.
SC also will not let you install unless you meet the requirements, so in our test environment I had to give my server 16G of ram and 6 cores just to get the install to move forward.
The requirements for the JBOSS server seem to have jumped dramatically, 5 sites is 21G of ram and 12 cores.
Has anyone else encountered these issues and have you found any solutions?
I honestly don't like the trend of GE forcing me to do anything (ram, cores, etc) seems like a bad indicator of what is to come.
SLHV, I've heard that from another user where it wouldn't let them move forward but from my understanding its just supposed to WARN you that you don't meet the recommendations and move forward. My test system VM is far below what is needed on purpose and it gives me a warning but still moves forward. Can you contact GE and see what they say. Please keep me posted.